Dear SAP WM Experts
I am new to SAP WM i am Trying to work on Automatic Bin Structure
i have one Storage type 10 in that i have High Bins and Low Bins and medium bins as Storage section.
if i want to Place Material under
1.Storage Type 10 under Storage section High Bins ( H1 ) from 1-01-01-01 to 01-04-04-11
2. Storage Type 10 under Storage section Low Bins ( l1 ) from 1-01-05-01 to 01-04-05-11
3.Storage Type 10 under Storage section Medium Bins( M1 ) from 1-01-06-01 to 01-04-06-11
my Question is i need to Create 3 Storage Types or 1 Storage Type with
WH1-10 -H1- Sequence (001)-1-01-01-01 to 01-04-04-11
WH1-10 -L1 Sequence (002) -1-01-05-01 to 01-04-05-11
WH110-M1 Sequence (001) - 1-01-06-01 to 01-04-06-11
WH1= Warehouse 1
10=Storage Type
H1 L1 M1= Storage Section
Sequnce
Thanks and Regards