Dear Maria,
Thanks for reply.
My query is how to update this date. Is automatic and manual?
Like when we create NWA and relation ship and WBS date planning, dates like basic date for WBS and Earliest/latest date for NWA will be updated automatically.
Now, project execution is started and its business practice that every 15 days we need to update dates. So, in such case, which dates we will update and how we will update?...if I understood correctly SAP Help...
....Dates for Internal Activities will be consider from confirmation. But, what about dates which will be consider for completion of balance work. where we need to updates?
....What about start date for external and service activity....where i need to mentioned and update this dates?
Hope I am able explain my concerns and requirement.
Regards
Rajat