Dear Experts,
During SOP, I configured properly the Rough-cut Capacity planning and it did worked in MC88 for rough-cut capacity leveling.
Then I tried to configured the required information for Material Leveling.
I created the rough-cut profile with the Raw Material that I want to check as a resource. I also created the Available Qty per period of time in MC9K (4000 M in this case, 1000 per month).
The material that is being evaluated is part of the BOM of the Material Planned in SOP.
But not rqmts appear in the Analysis (Table S093).
I will appreciate your advice.
Thanks in advance.
Regards,